Whitefriars Wharf: external waterproofing

Parapet gutter renewal, coping leadwork and external remedial repairs, supported by site photographs and progress reports.

Whitefriars Wharf: external waterproofing

Client: PJJS Management Services. Location: Whitefriars Wharf, Tonbridge. External programme completed: 14 October 2026. Case study updated: 16 October 2026.

The water-ingress problem

The external programme addressed defective parapet gutter decks, waterproofing and coping details. Debris, failed joints and areas of standing water required preparation and repairs before renewing the waterproofing.

Preparation, renewal and recorded results

The programme included removing defective coverings and boarding where required, fitting replacement marine-plywood decks, adjusting deck levels towards the existing outlets, and cleaning and priming the gutter floors and upstands. New membrane was installed across the prepared surfaces, with sealed laps, returns and outlet details. Work was recorded separately by area across both blocks.

Debris and contamination in a parapet gutter before preparation
BeforeWeek 6 site record: gutter condition before preparation.
Existing defective gutter joint
Repair detailWeek 6 site record: an existing joint requiring attention.
Renewed plywood gutter deck during preparation
DuringDeck preparation photographed during the external programme.
Renewed membrane along a parapet gutter
Completed areaWeek 6 site record: renewed gutter waterproofing.
Membrane and leadwork at the parapet gutter
External detailingMembrane and coping leadwork photographed during the programme.
Dry undercroft floor photographed after rainfall
Observed resultThe report recorded a dry undercroft floor after rainfall. Further heavy-rain monitoring was recommended.

Final stages: Block 1

The final membrane-only renewal was completed on 12 October, followed by repointing beneath the coping stones on 13 October. At the L-shaped gutter, the corner was raised to direct water towards the outlets at both ends. The longer leg was completed on 13 October and the short return on 14 October, concluding the scheduled external programme.

Existing gutter and abutment before membrane renewal, photographed on 12 October 2026.
Before · Block 1 membrane renewalExisting gutter and abutment before membrane renewal, photographed on 12 October 2026.
Cleaned and primed gutter at the abutment, photographed on 12 October 2026.
During · surface preparationCleaned and primed gutter at the abutment, photographed on 12 October 2026.
Completed Block 1 gutter membrane, photographed on 12 October 2026.
After · renewed membraneCompleted Block 1 gutter membrane, photographed on 12 October 2026.
Standing water before deck reconstruction, photographed on 13 October 2026.
Before · L-shaped gutterStanding water before deck reconstruction, photographed on 13 October 2026.
Replacement deck fitted along the L-shaped gutter during the 13–14 October works.
During · new marine-plywood deckReplacement deck fitted along the L-shaped gutter during the 13–14 October works.
Completed L-shaped gutter, photographed on 14 October 2026.
After · final gutter areaCompleted L-shaped gutter, photographed on 14 October 2026.

Completed work packages

The final parapet-gutter completion report was issued on 15 October 2026. Earlier completed areas are retained in the project record rather than presented as new work.

Work packageCompletionRecorded scope
Block 2 · five gutter areasSeptember–early October 2026Deck renewal, preparation and membrane installation, with falls adjusted where required.
Block 1 · earlier gutter renewalLate September–early October 2026Cleaning, substrate preparation and membrane renewal, including the outlet detail.
Block 1 · membrane renewal area12 October 2026Failed membrane removed; gutter and upstands cleaned, primed and relined. Associated repointing completed 13 October.
Block 1 · final L-shaped gutter14 October 2026Marine-plywood deck reconstruction, raised corner, falls towards both outlets, priming and membrane renewal.

Related external work

Coping-stone lead weathering and separately instructed coping repairs formed other work packages within the wider external programme. Local cracked brickwork was also repaired using resin-bedded helical bars and repointing, recorded complete on 8 October. These masonry repairs are distinct from the gutter membrane renewals.

External work only

This case study records the external programme. Internal water-damage repairs and lift-shaft reinstatement are separate scopes and are not presented as completed within this project.

What the observation tells us

The earlier dry undercroft photographs record conditions following rainfall. James also reported that next-day checks after rain found no water build-up in completed areas. These are observations at those visits, not a separate controlled flow or flood test or a guarantee that every water-ingress issue across the development is resolved. Future aftercare includes returning to inspect the completed work and keeping the gutter runs and outlets clear. Photographs record the deck surfaces and membrane stages; they do not show every concealed fall-forming support.

A separate completed plumbing-leak investigation and internal reinstatement project is documented in our concealed plumbing leaks case study.

Property and estate maintenance · Roofing and guttering

Have a similar project?

Send photographs and a brief description of the work to help us discuss the scope and access required.

Discuss your project

Or call 07341 447014.