Client: PJJS Management Services. Location: Whitefriars Wharf, Tonbridge. External programme completed: 14 October 2026. Case study updated: 16 October 2026.
The water-ingress problem
The external programme addressed defective parapet gutter decks, waterproofing and coping details. Debris, failed joints and areas of standing water required preparation and repairs before renewing the waterproofing.
Preparation, renewal and recorded results
The programme included removing defective coverings and boarding where required, fitting replacement marine-plywood decks, adjusting deck levels towards the existing outlets, and cleaning and priming the gutter floors and upstands. New membrane was installed across the prepared surfaces, with sealed laps, returns and outlet details. Work was recorded separately by area across both blocks.






Final stages: Block 1
The final membrane-only renewal was completed on 12 October, followed by repointing beneath the coping stones on 13 October. At the L-shaped gutter, the corner was raised to direct water towards the outlets at both ends. The longer leg was completed on 13 October and the short return on 14 October, concluding the scheduled external programme.






Completed work packages
The final parapet-gutter completion report was issued on 15 October 2026. Earlier completed areas are retained in the project record rather than presented as new work.
| Work package | Completion | Recorded scope |
|---|---|---|
| Block 2 · five gutter areas | September–early October 2026 | Deck renewal, preparation and membrane installation, with falls adjusted where required. |
| Block 1 · earlier gutter renewal | Late September–early October 2026 | Cleaning, substrate preparation and membrane renewal, including the outlet detail. |
| Block 1 · membrane renewal area | 12 October 2026 | Failed membrane removed; gutter and upstands cleaned, primed and relined. Associated repointing completed 13 October. |
| Block 1 · final L-shaped gutter | 14 October 2026 | Marine-plywood deck reconstruction, raised corner, falls towards both outlets, priming and membrane renewal. |
Related external work
Coping-stone lead weathering and separately instructed coping repairs formed other work packages within the wider external programme. Local cracked brickwork was also repaired using resin-bedded helical bars and repointing, recorded complete on 8 October. These masonry repairs are distinct from the gutter membrane renewals.
This case study records the external programme. Internal water-damage repairs and lift-shaft reinstatement are separate scopes and are not presented as completed within this project.
What the observation tells us
The earlier dry undercroft photographs record conditions following rainfall. James also reported that next-day checks after rain found no water build-up in completed areas. These are observations at those visits, not a separate controlled flow or flood test or a guarantee that every water-ingress issue across the development is resolved. Future aftercare includes returning to inspect the completed work and keeping the gutter runs and outlets clear. Photographs record the deck surfaces and membrane stages; they do not show every concealed fall-forming support.
A separate completed plumbing-leak investigation and internal reinstatement project is documented in our concealed plumbing leaks case study.
Property and estate maintenance · Roofing and guttering
Have a similar project?
Send photographs and a brief description of the work to help us discuss the scope and access required.
Discuss your projectOr call 07341 447014.